Corrimont Medical

Two plants became one without a missed shipment or a failed audit.

Plant consolidation

·

16 weeks

A doctor talking with a parent and child in a clinic

Medical devices

·

2024

Corrimont Medical

Two plants became one without a missed shipment or a failed audit.

Plant consolidation

·

16 weeks

A doctor talking with a parent and child in a clinic

Medical devices

·

2024

Corrimont Medical

Two plants became one without a missed shipment or a failed audit.

Plant consolidation

·

16 weeks

A doctor talking with a parent and child in a clinic

Medical devices

·

2024

■ About the client

Corrimont makes single-use surgical devices for hospitals across Europe. It ran two ageing plants forty miles apart, each of them half full.

■ About the client

Corrimont makes single-use surgical devices for hospitals across Europe. It ran two ageing plants forty miles apart, each of them half full.

■ About the client

Corrimont makes single-use surgical devices for hospitals across Europe. It ran two ageing plants forty miles apart, each of them half full.

Client

Corrimont Medical

Medical devices

2→1

Plants, no missed shipments

Brief

Consolidate two plants into one without a missed shipment or a failed audit.

Production moved in four waves over sixteen weeks. Every shipment left on time and both regulatory audits passed first time.

Outcome

Client

Corrimont Medical

Medical devices

2→1

Plants, no missed shipments

Brief

Consolidate two plants into one without a missed shipment or a failed audit.

Production moved in four waves over sixteen weeks. Every shipment left on time and both regulatory audits passed first time.

Outcome

Client

Corrimont Medical

Medical devices

2→1

Plants, no missed shipments

Brief

Consolidate two plants into one without a missed shipment or a failed audit.

Production moved in four waves over sixteen weeks. Every shipment left on time and both regulatory audits passed first time.

Outcome

The brief

Corrimont’s board had approved the move twice and stopped it twice. Each time, the risk to regulated production looked too large to plan around.

The brief

Corrimont’s board had approved the move twice and stopped it twice. Each time, the risk to regulated production looked too large to plan around.

The brief

Corrimont’s board had approved the move twice and stopped it twice. Each time, the risk to regulated production looked too large to plan around.

What we did

We built the move line by line with the plant managers, sequenced it in four waves around stock builds, and ran a validation plan the quality team signed before a single machine moved.

What we did

We built the move line by line with the plant managers, sequenced it in four waves around stock builds, and ran a validation plan the quality team signed before a single machine moved.

What we did

We built the move line by line with the plant managers, sequenced it in four waves around stock builds, and ran a validation plan the quality team signed before a single machine moved.

What held

The second plant closed on schedule. Output per shift is up eleven per cent, and the site passed its first audit after the move with no findings.

What held

The second plant closed on schedule. Output per shift is up eleven per cent, and the site passed its first audit after the move with no findings.

What held

The second plant closed on schedule. Output per shift is up eleven per cent, and the site passed its first audit after the move with no findings.

Corrimont Medical

They planned it with the people who run the lines, which is why it worked.

Henrik Aalto

Plant Director

Corrimont Medical

They planned it with the people who run the lines, which is why it worked.

Henrik Aalto

Plant Director

Corrimont Medical

They planned it with the people who run the lines, which is why it worked.

Henrik Aalto

Plant Director